Virginia DEQ
Home MenuDominion Chesterfield Energy Reliability Center Project
Chesterfield Power Station Project Summary – Chesterfield Energy Reliability Center (CERC) Project
In January 2018, Dominion Energy (Dominion) stopped using their two coal-fired boilers #3 and #4 and shut them down on March 31, 2019. Coal boilers #5 and #6 were shut down on May 31, 2023. The facility no longer combusts coal in any units.
DEQ received revised Prevention of Significant Deterioration (PSD) permit applications for the CERC project on August 1, 2023 and March 3, 2025. Dominion is seeking a PSD permit for a simple-cycle electrical generating station to be located on the site of the Chesterfield Power Station. Dominion states the purpose of this project is to “support the clean energy transition while optimizing reliability and economics” for their system customers.
Proposed equipment:
- Four 250 MW simple-cycle combustion turbines, capable of combusting natural gas, natural gas with hydrogen (up to 10%), and low sulfur #2 distillate fuel oil.
- Seven 3,500 kW black start generators firing ULSD.
- Several circuit breakers, using SF6 as an insulating gas.
- Eight fixed-roof fuel oil storage tanks (one 12 million gallons and seven 3,500 gallons)
- Fugitive emissions from piping components
Proposed emissions from facility (tons/year):
PM |
PM10 |
PM25 |
SO2 |
NOx |
CO |
VOC |
Pb |
H2SO4 |
CO2e |
81.8 |
153.9 |
153.9 |
27.8 |
353.3 |
825.3 |
162.5 |
0.063 |
18.7 |
2.2 million |
Turbine emission include startups and shutdowns (firing both natural gas or fuel oil)
The facility is already considered a major source of HAP emissions. The proposed annual HAP emissions from this project: Maximum individual HAP, 5.07 tons of formaldehyde, Total HAP: 13.5 tons.
Proposed permitting timeline: Permitting Enhancement and Evaluation Platform (PEEP)
Dominion Energy, Inc. Presentation - Chesterfield Energy Reliability Center (July 2023)
Air Permit Application for the Chesterfield Energy Reliability Center (August 2023)
DEQ Initial Letter of Determination (August 2023)
Public Notice of Public Information Briefing on November 16, 2023
Chesterfield County Zoning Letter (June 2024)
(Espanol) Carta a SCC y DEQ de Chesterfield Co (junio de 2024)
DEQ Zoning Letter Response (July 2024)
Carta a Joseph Casey (julio de 2024)
CERC Application Supplement: Relocation (August 2024)
DEQ Review of Supplemental Information (September 2024)
DEQ Response to Request for Extension (September 2024)
Dominion Response Regarding Revised Site Suitability (September 2024)
DEQ Review of Additional Information (October 2024)
Updated Air Permit Application for the Chesterfield Energy Reliability Center (March 2025)
DEQ Acknowledgement/Review Letter (March 2025)
PSD Air Quality Impact Analyses Report for the Chesterfield Energy Reliability Center (May 2025)
Public Notice of Public Information Briefing on August 7, 2025
PowerPoint Presentation: Chesterfield Energy Reliability Center DEQ Public Briefing (August 7, 2025)
Fact sheet: CERC PSD (August 7, 2025)
Hoja informativa: CERC (Espanol) (7 de agosto de 2025)
Public Notice of Public Comment Period (August 8 to October 8, 2025) and Public Hearing on September 8, 2025 (Dominion Energy)
DEQ Public Notice of Public Comment Period (August 8 to October 8, 2025) and Public Hearing on September 8, 2025
Permit Application / Permit Application Appendices
Draft Permit
Draft Engineering Analysis